-
DESTINATION MOON: A History of the
Lunar Orbiter Program
-
-
- CHAPTER XI: CONCLUSIONS: LUNAR
ORBITER'S CONTRIBUTION TO SPACE EXPLORATION
-
- A Sixth Orbiter
Mission?
-
-
-
- [303] Even before
Lunar Orbiter V flew, the Office of Space Science and Applications
was entertaining the prospect of flying a sixth Orbiter mission.
Boeing had nearly enough parts to assemble another spacecraft at
an initial cost of about $13 million. A gamma-ray experiment also
existed which scientists desired to fly on a sixth Orbiter. Its
inclusion would raise the cost of the mission by about $3 million.
However, the necessity to relocate personnel on the Lunar Orbiter
team to other jobs presented a major problem blocking another
mission.1
-
- Lunar Orbiter Program officials estimated
that if the mission of Lunar Orbiter
V failed, the program would have to
fly a sixth Orbiter. However, refurbishment of a sixth spacecraft
required such parts as two new solar panels. The Lunar Orbiter
Program Office examined the needs and the lead times required for
a sixth mission during May and June 1967. By the beginning of July
program management knew that OSSA soon had to make a commitment to
another mission if it wanted [304] to avoid major
shifts of personnel at Langley and Boeing following the
photographic phase of Mission V. Known, too, was the simple fact
that the longer NASA officials waited to approve the go-ahead for
a new mission, the greater the costs and the more severely the
management arrangements would impact on other NASA
programs.2
-
- On July 5 Scherer issued a statement
summarizing the objectives of the fifth mission and the rationale
behind a sixth Orbiter flight. He pointed out that the total cost
of each of the first five missions amounted to $40 million apiece.
The sixth mission would cost less than one third of this. Even if
the fifth mission successfully achieved all planned objectives, a
sixth mission could accomplish very valuable and different goals.
Briefly it could 1) perform a total survey of the far side of the
Moon at 60 to 80 meters resolution, 2) take a concentrated look at
the best Apollo Program sites as determined through analysis of
photographic data from the fifth mission, and 3) closely survey
additional areas of high scientific interest. If Mission E
failed,3 a Mission F would be necessary according to
Scherer.4
-
- [305] The Lunar
Orbiter Project Office at Langley sent a memorandum to Scherer's
Office on July 12 detailing the options open to OSSA for a sixth
mission. The first option required a go-ahead decision by
mid-July. The details were these: 1) that refurbishment and
processing the spacecraft required four months and was the pacing
item; 2) cost of launching Lunar Orbiter F late in November would
amount to $12.75 million; 3) a launch by that time would retain
the launch readiness capability of the previous launches; 4) this
option provided the greatest retention of overall experience in
the Lunar Orbiter team.5 The second option was the same as the first except
that it allowed for cancellation of preparations for a sixth
flight early in September. At that time, data from Lunar Orbiter V would
be available. If the mission was successful and the need for
another mission was insufficiently justified, then the Lunar
Orbiter Program could cancel the additional mission at a cost of
about $4 million.6
-
- The third option was the least manageable.
It required that NASA postpone the July go-ahead but authorize
funds to hold the team and the hardware in readiness until
evaluation of the Lunar Orbiter
V mission results. This option
would [306] extend the earliest possible launch date from late
November 1967 to late January 1968 and raise the cost of a sixth
mission to $16.5 million. It would also impact on the launch of
OGO-E (Orbiting Geophysical Observatory satellite E) and would
delay the Air Force takeover of Launch Complex 13 at Cape Kennedy.
In view of these circumstances the Langley Lunar Orbiter Project
Office recommended that only the first option be considered and
that NASA Headquarters approve go-ahead before July 22,
1967.7
-
- On July 14, 1967,Homer E. Newell sent NASA
Deputy Administrator Robert C. Seamans, Jr., a summary of the
alternatives for a sixth mission. He reiterated the three options
which the Langley memorandum had specified and underlined
Langley's position in support of a July go-ahead for a late
November launch. He stressed to Seamans that a delayed decision
would affect management problems, costs, and schedules in the
Office of Space Science and Applications.8
-
- Seamans weighed the need for a sixth
mission and decided that NASA funds would better support other
activities. On July 24, 1967, Scherer officially informed Langley
that NASA [307] Headquarters had decided against a sixth Lunar
Orbiter mission. However, he stated in his telegram to Floyd L.
Thompson that a remote possibility for a reversal existed if the
fifth mission failed. He requested Langley to proceed to phase out
the program but to retain mission-peculiar test, launch, and
flight operations equipment until it had completed the photo
readout of Mission V. This retention did not apply to personnel,
and Langley was to commence reassignment.9
-
- Because Lunar Orbiter V
succeeded beyond expectations in carrying out its mission
objectives, its Achievements proved that the cancellation of a
sixth mission had been a prudent move. Moreover, the Apollo
Program had virtually no need for the kind of data a sixth mission
might have obtained; it would not have been decisive in mission
planning. Indeed, at the Apollo Site Selection Board meeting on
March 30s 1967, Apollo Program officials agreed that, "although
further data from Lunar Orbiters D and E will be requested., the
photography already received from Orbiters I. II, and III meets
the minimal requirements of the Apollo Program for site survey for
the first lunar landing."10 They arrived at this conclusion [308] by detailed
screenings of Lunar orbiter data using the following steps:
-
- 1. Construct Lunar Module landing ellipses
and radar approach templets from photo support data.
-
- 2. Outline reject areas on medium
resolution photographs.
-
- 3. Scan remaining area where
high-resolution coverage is also available.
-
- 4. Select better ellipse locations with
favorable radar approaches. Identify obstacles.
-
- 5. Select best ellipse based on landing
and radar obstacles, count craters, and compute 'N' number from
medium-resolution photos. For most favorable sites continue
evaluation with high-resolution photography.
-
- 6. Evaluate ellipses on high-resolution
photography and compute 'N' number.11
-
-
-

